Measures the amount of work completed in a sprint in story points. Predicts capacity and enables accurate release planning.

Hướng dẫn từng bước

  1. 1Estimate story points per task (Fibonacci: 1, 2, 3, 5, 8)
  2. 2Complete sprint (1-2 weeks)
  3. 3Sum story points of completed items
  4. 4Track velocity over multiple sprints
  5. 5Use average for planning

Ví dụ có lời giải

đầu vào
50pts/2wk
Kết quả
25pts/week

Lỗi thường gặp cần tránh

  • Including incomplete items in velocity
  • Adding scope mid-sprint without removing items

Câu hỏi thường gặp

What velocity indicates maturity?

New teams: 20-40 points; established: 50-100; high-performance: 100-150+ depending on team size.

What affects velocity?

Team composition, interruptions, estimation accuracy, and technical debt.