Calculates the maximum time allowed per unit to meet production targets. Sets the pace for production planning.
공식
Formula: takt time = available time ÷ target units
단계별 가이드
- 1Available production time per day (minutes)
- 2Daily production target (units)
- 3Formula: takt time = available time ÷ target units
- 4One unit must complete in less than takt time
풀어진 예시
입력
480min/day, 100u
결과
4.8 min/unit
피해야 할 일반적인 실수
- ✕Confusing takt time (pace) with cycle time (actual)
- ✕Not adjusting for breaks and changeovers
자주 묻는 질문
Why is takt time important?
Provides production target pace; identifies if current speed can meet demand.
How do I reduce takt time?
Increase available time (extend hours), or reduce target (fewer units needed).