Skip to main content
DigiCalcs

Cara Menghitung Earned Value

learn.whatIsHeading

Measures project progress by comparing work completed to budget spent. Identifies if projects are ahead, on-track, or behind schedule/budget.

Rumus

SPI = EV ÷ PV (schedule performance)
SPI
EV ÷ PV (schedule performance) — EV ÷ PV (schedule performance)
EV
EV value — Variable used in the calculation
PV
PV value — Variable used in the calculation

Panduan Langkah demi Langkah

  1. 1Planned Value (PV): budgeted cost for work scheduled
  2. 2Earned Value (EV): budgeted cost of completed work
  3. 3Actual Cost (AC): real cost spent
  4. 4SPI = EV ÷ PV (schedule performance)
  5. 5CPI = EV ÷ AC (cost performance)

Contoh Terpecahkan

Masukan
80% done, $1M
Hasil
$800k EV

Kesalahan Umum yang Harus Dihindari

  • Not updating progress regularly (weekly minimum)
  • Misaligning earned value with actual completion percentage

Pertanyaan yang sering diajukan

What do SPI and CPI indicate?

SPI >1 ahead schedule, <1 behind; CPI >1 under budget, <1 over budget.

How do I forecast final cost?

Estimate at Completion (EAC) = BAC ÷ CPI; shows final cost if current performance continues.

Siap menghitung? Coba Kalkulator Earned Value gratis

Cobalah sendiri →

Pengaturan

PrivasiKetentuanTentang© 2026 DigiCalcs