Skip to main content
Skip to main content
DigiCalcs

How to Calculate Earned Value

What is Earned Value?

Measures project progress by comparing work completed to budget spent. Identifies if projects are ahead, on-track, or behind schedule/budget.

Formula

SPI = EV ÷ PV (schedule performance)
SPI
EV ÷ PV (schedule performance) — EV ÷ PV (schedule performance)
EV
EV value — Variable used in the calculation
PV
PV value — Variable used in the calculation

Step-by-Step Guide

  1. 1Planned Value (PV): budgeted cost for work scheduled
  2. 2Earned Value (EV): budgeted cost of completed work
  3. 3Actual Cost (AC): real cost spent
  4. 4SPI = EV ÷ PV (schedule performance)
  5. 5CPI = EV ÷ AC (cost performance)

Worked Examples

Input
80% done, $1M
Result
$800k EV

Common Mistakes to Avoid

  • Not updating progress regularly (weekly minimum)
  • Misaligning earned value with actual completion percentage

Frequently Asked Questions

What do SPI and CPI indicate?

SPI >1 ahead schedule, <1 behind; CPI >1 under budget, <1 over budget.

How do I forecast final cost?

Estimate at Completion (EAC) = BAC ÷ CPI; shows final cost if current performance continues.

Ready to calculate? Try the free Earned Value Calculator

Try it yourself →

Settings

PrivacyTermsAbout© 2026 DigiCalcs